Viewing 1 reply thread
  • Author
    Posts
    • Rahul Menon
      Member
      Post count: 27

      Hi team,

      I am using your task management system, but i have a requirement. Please mention if it is possible in our software.

      My requirement is, I have a task for weekly meeting. Now am creating a task on every week.
      Is it possible to recur a task on every week?
      If possible, it is much helpful for us.
      Please reply

      Regards,
      Rahul
      Global Web Solutions

    • muneer
      Member
      Post count: 78

      Recurring task

      In tasks under ess, we have an option for recurring tasks.

      Just simply do the following things:
      1. Create a task
      2. Click the recurring button   in the top
      3. Select the interval weekly and choose a due day
      4. Click save

      Then the task will recur if you completed that task.

      This option is available only in the Lenvica HRMS updates from 3.8.76